This case study is typical of a construction company not taking advice from ground water control experts.
As can be observed from the attached photo, the contractor has made some fundamental mistakes
- After installing I-beam and concrete segmented shoring, they proceded to excavate, without taking into account possible pre-existing ground water control requirements.
- After excavating to the initial RL seen here, there was no ground water concerns, and the site was dry.
- After a lengthy period of no further site activity, or mobilisation of the dewatering contractor's scope of works, water inflows started, possibly as a result of dewatering operations being concluded and switched off from surrounding sites.
- There is no suitably dry platform for the piling contractors to work from, or for the dewatering contractors's drill rig, to install deepwells.
- The shoring, as can be seen, is not suitable for the conditions, as it cannot provide a sufficiently watertight cutoff from transverse water flow.
- A dry working platform for the piling contractor and dewatering contractor is unobtainable at this stage
- The point of discharge is around 2 kilometers away into a stormwater drain.
Observe the mound of backfill material in the left of photo. This is how the contractor has decided on his own methods to retrieve the situation, by trying to backfill the excavation, in defiance of the expert advice provided.
We'll follow this example to its logical conclusion, as a case study on how NOT to excavate a site.
7 comments:
ACTION International Services is a customer oriented, ISO certified, company providing engineered solutions in the field of Ground Water Control / Dewatering, Industrial Services, Specialized Equipment Rental, Piling and Ground Engineering Works.
What makes us different?
Leadership | Teamwork | Customer Focus | Responsibility | Innovation | Integrity | Passion
ACTION International Services is a customer oriented, ISO certified, company providing engineered solutions in the field of Ground Water Control / De-watering with offices in Dubai, Abu Dhabi , Qatar , Oman and Saudi Arabia. website is WWW.action-is.com
I got this blog very informative and true thing is that dewatering is the process of removing unwanted water, through dewatering submersible pumps, often required for excavation purposes in construction and civil engineering projects.
Nice post,Thanks for sharing the information about Dewatering.Dewatering pumps
https://www.blogger.com/comment.g?blogID=1224023453961247887&postID=5336800283612942252&page=1&token=1570616208484&isPopup=true
Positive site, where did u come up with the information on this posting? I'm pleased I discovered it though, ill be checking back soon to find out what additional posts you include. Badger Trench Box
I am impressed. I don't think Ive met anyone who knows as much about this subject as you do. You are truly well informed and very intelligent. You wrote something that people could understand and made the subject intriguing for everyone. Really, great blog you have got here. trench shore
Post a Comment